Construction Update: Highway 1416 Sanitary Sewer Project
The City of Box Elder will be providing updates to the public regarding current and anticipated impacts to traffic flows and construction activities related to the Highway 14/16 Sanitary Sewer Upgrades project. Updates will be posted on a weekly basis to the City’s website on our Engineering Department’s page and the News Section of our homepage. Updates will also be posted to the City’s Facebook and Instagram accounts.
Weekly Project Highlights:
April 7 to April 11:
• Manhole rehabilitation work to continue on Box Elder Road.

Minor traffic impacts on Box Elder Road, with a lane closure around MHs.
• Work continues in the Highway 1416 median on the eastern most end of the project.
• No impact on the N Ellsworth Rd and Highway 1416 intersection.
• Work may include activities adjacent to Highway 1416 driving lanes, but all lanes will remain open.

Important Note – This work will impact the Oak Street Crossover.
April 14 to April 18:
• Completion of manhole rehabilitation on Box Elder Road expected.
• Work continues in the Highway 1416 median on the eastern end of the project
• No impact on the N Ellsworth Rd and Highway 1416 intersection.
• Work may include activities next to Highway 1416, but all lanes will remain open.